INSTALLATION
1. INSTALL VENTILATION VALVE SUB-ASSEMBLY
2. INSTALL VENTILATION VALVE COVER
3. INSTALL CRANKSHAFT POSITION SENSOR
4. INSTALL KNOCK CONTROL SENSOR
5. INSTALL VVT SENSOR
6. INSTALL CAMSHAFT TIMING OIL CONTROL VALVE ASSEMBLY LH
7. INSTALL CAMSHAFT TIMING OIL CONTROL VALVE ASSEMBLY RH
8. INSTALL FRONT NO. 1 ENGINE MOUNTING BRACKET LH
|
(a) Install the mounting bracket with the 4 bolts.
Torque: 36 N·m (367 kgf·cm, 27 ft·lbf)
|
9. INSTALL FRONT NO. 1 ENGINE MOUNTING BRACKET RH
|
(a) Install the mounting bracket with the 4 bolts.
Torque: 36 N·m (367 kgf·cm, 27 ft·lbf)
|
10. INSTALL FRONT ENGINE MOUNTING INSULATOR LH
|
(a) Install the mounting insulator with the nut.
Torque: 72 N·m (734 kgf·cm, 53 ft·lbf)
|
11. INSTALL FRONT ENGINE MOUNTING INSULATOR RH
|
(a) Install the mounting insulator with the nut.
Torque: 72 N·m (734 kgf·cm, 53 ft·lbf)
|
12. INSTALL NO. 2 WIRING HARNESS HEAT INSULATOR
|
(a) Install the heat insulator with the 2 bolts.
Torque: 17 N·m (173 kgf·cm, 13 ft·lbf)
|
13. INSTALL OIL COOLER PIPE
14. INSTALL REAR WATER BY-PASS JOINT
15. INSTALL FRONT WATER BY-PASS JOINT
16. INSTALL INLET WATER HOUSING
17. INSTALL STARTER ASSEMBLY
18. INSTALL NO. 4 AIR INJECTION SYSTEM HOSE
19. INSTALL AIR PUMP ASSEMBLY
20. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY
21. INSTALL AIR TUBE
|
(a) Install the gasket and air tube with the 3 bolts.
Torque: 10 N·m (102 kgf·cm, 7 ft·lbf)
Torque: 16 N·m (163 kgf·cm, 12 ft·lbf)
|
22. INSTALL INTAKE MANIFOLD
23. INSTALL NO. 3 WATER BY-PASS PIPE
24. INSTALL VACUUM HOSE ASSEMBLY
25. INSTALL IGNITION COIL ASSEMBLY
26. INSTALL AIR SWITCHING VALVE ASSEMBLY (for Bank 2)
27. INSTALL NO. 2 AIR TUBE HOSE
28. INSTALL AIR SWITCHING VALVE ASSEMBLY (for Bank 1)
|